If you’ve been to the health centre lately, you will have noticed that we’ve rearranged a few things and moved some people around. This is because our heating system, which has reached end of life, as well as lighting throughout the building are being replaced. The project has been split into seven phases, with phase one having started in March.
Mid-May will see us transition to phase two which will change the flow of traffic in the building. The main entrance, waiting area, and main reception will be closed for this phase of renos. Patients and public will be redirected to the Ambulance/Physiotherapy door at the end of the building and the temporary reception and waiting area will be in the Physiotherapy spaces until the end of this phase.
As we progress trough the remaining phases of this major renovation, I will provide further updates to keep you informed of changes in how you access our services and travel through the building.
Thank you for your patience and understanding as we all adapt to these temporary changes.